Brazil

Brazil Smart Metering Case

#Smart Metering

  • Quantity

    1000000

  • Communication Solution

    Wi-Sun、4G

  • Collection Rate

    98%

  • System

    HES、MDM、NMS

  • Customer Satisfaction

    99%

Follow us

Project Background

Long response time for grid failure

Low digitalization of grid management

Poor accuracy of grid analysis and high cost of maintenance

Solutions

Scale: Currently 1 million meters installed, with a total contract of 2.8 million meters-making it one of the largest AMI deployments in South America.


Solution: We deployed Wi-SUN technology-our first self-developed Wi-SUN project. This mesh networking technology is ideal for dense urban environments and areas with challenging communication conditions.


Performance: We achieved a 98% collection rate, with particular success in "isolated island" areas where communication is traditionally difficult. The mesh network automatically routes around obstacles, ensuring reliable data collection even in challenging locations.


Value: The completed installation of 1 million smart meters in 2025 generated $11.2 million in value for our client. At full deployment of 9 million consumers, the client could achieve annual value of $86 million.


Systems Deployed: SanPlat™ MDC (Meter Data Concentrator), NMS (Network Management System), and MDM — our complete software stack.


Client Satisfaction

This project has improved our analytical capabilities to identify non-technical losses of consumers, increasing our inspection accuracy by more than 50%.

Together for a Smarter Grid

<